How to complete a pull transfer process #4594
-
Guys, in a pull transfer the transfer process keeps in started status infinitely, either after the consumer calls the /public on the provider to get the transfer data. How can I change the pull transfer process to completed ? I only found on the management API an endpoint to terminate the transfer, but not one to successfully complete it. Regards, |
Beta Was this translation helpful? Give feedback.
Answered by
ndr-brt
Oct 31, 2024
Replies: 1 comment
-
Hi, I suggest to look at the documentation: https://eclipse-edc.github.io/documentation/for-contributors/control-plane/policy-monitor/ |
Beta Was this translation helpful? Give feedback.
0 replies
Answer selected by
jannotti-glaucio
Sign up for free
to join this conversation on GitHub.
Already have an account?
Sign in to comment
Hi, I suggest to look at the documentation: https://eclipse-edc.github.io/documentation/for-contributors/control-plane/policy-monitor/