GitHub Projects
Field | Description |
---|---|
Project | The top level initiative or product set example (orchestration API) |
Component | area within a project (defined feature, product, or effort set delivered to a customer) |
Release | The planned upgrade or coreEval the item is assigned to |
Priority | Importance to a release. P1 must ship in the release. P2 is good. P3 should not. P0 trumps all. Engineers should work on the highest priority items in their purview. Priority is driven by a combination of inputs including the upgrade an item is planned for as well as other company needs and dependencies. |
Effort | The effort needed to complete this item, in number of days expected. Estimated by assignee and their peers. Range 0.5 - 5.0 |
Delivery Estimate | used in project management to generate reports, forecasted from Effort estimates and backlog (optional, dates for open issues never in the past) |
Sprint | when a team has committed to deliver it (set in sprint kickoff) |
Dependencies between issues are expressed in a Tasklist named "Dependencies"
Code Complete, 0 Days date for all work items to be reviewed and closed
Mainnet Clone Testing, 3 Days
testing against a network mirroring mainnet with data and infra
Emerynet Announcement, 3 Days
opco pledged to announce coming emerynet testing 3 days prior to planned testing(flexible)
Emerynet deploy & Testing, 3 Days
validators and opco testing on a shared public test-net for quality and transparency
Mainnet Announcement, 3 Days
We pledged to announce coming emerynet testing 3 days prior to planned testing
Mainnet Proposal & Voting, 3 Days
required 72 open voting period per chain bylaws
Mainnet Upgrade, 0 Days
The process of validators performing a coordinated synced upgrade (watchparty)
Mainnet Testing, 2 Days
Required testing period for validations of any changes on mainnet
Mainnet Validated, 0 Days
all is well, done and done
- Open/ Backlog - new or unaddressed items which are to be addressed during triage sessions
- Up Next - triaged and placed into the assignee's que (assignee)
- In Progress - Currently being solved by the assignee (assignee)
- Code Complete - Work done by assignee, needs deployment to chain
- Releasing - Item has been pulled into a release branch intended for deployment
- Emerynet Validated - Item has been tested as part of the release branch on Emerynet
- Mainnet Validated - (done) Item has been tested as part of the release branch on Mainnet